- Owner · Project sponsor: Desert Southwest Pipeline
Synopsis
Energy Transfer LP is an energy-infrastructure partnership with natural-gas, crude-oil, natural-gas-liquids, and refined-products assets. Its subsidiary Transwestern Pipeline Company, LLC is sponsoring the proposed Desert Southwest Pipeline expansion from West Texas through New Mexico into Arizona.
Energy Transfer announced a positive final investment decision on August 6, 2025. That announcement described 516 miles of 42-inch pipeline, 1.5 billion cubic feet per day of design capacity, nine compressor stations, an estimated cost of about $5.3 billion, and expected service in the fourth quarter of 2029. Current applicant materials describe an approximately 520-mile project capable of delivering up to 2.3 billion cubic feet per day. Those later figures should be used as the current applicant description, while recognizing that engineering and environmental review remain underway.
Transwestern is using FERC’s pre-filing process under PF26-9-000. Pre-filing is not a construction certificate or project approval. APS, the City of Mesa, Salt River Project, Tucson Electric Power, and UniSource Energy Services separately announced commitment plans for the expansion. The public sources do not establish that any particular Desert Southwest capacity is dedicated to the Saguaro Power Plant expansion.
Links
Corporate information
Official information
Corporate records
Corporate news
Project announcements
Project updates
Applicant project resources
Official FERC records
Utility commitments
Government statements
Connected entity profiles
Connected project profiles
Sources from connected projects
- Desert Southwest Pipeline FERC Desert Southwest Expansion Project
- Desert Southwest Pipeline FERC eLibrary
- Desert Southwest Pipeline Notice — PF26-9-000
- Desert Southwest Pipeline Coolidge scoping session
- Desert Southwest Pipeline FERC eComment
- Desert Southwest Pipeline FERC Online and eFiling
- Desert Southwest Pipeline FERC eSubscription
- Desert Southwest Pipeline Desert Southwest project page
- Desert Southwest Pipeline Desert Southwest FAQs
- Desert Southwest Pipeline Energy Transfer announces Desert Southwest project
- Desert Southwest Pipeline Transwestern binding open season announcement
- Desert Southwest Pipeline Energy Transfer first-quarter 2026 project update
- Desert Southwest Pipeline Arizona utilities announce commitment plans
- Desert Southwest Pipeline ACC statement on utility commitments
Timeline & Milestones
Scroll or swipe to explore
How to get involved
Participation guides not yet published. Step-by-step ways to take part will appear here when this profile is completed.
Upcoming
No upcoming events currently posted.
Past events
FERC scoping comments due — Desert Southwest Pipeline
Deadline for public input on FERC pre-filing environmental scoping. Docket PF26-9-000. Energy Transfer / Transwestern expansion, ~520 miles, 48-inch, up to 2.3 Bcf/d Permian-to-Arizona/New Mexico.
- Full date and time
- Wednesday, August 5, 2026
- Status
- Completed
Related projects: Desert Southwest Pipeline
Related entities: Energy Transfer LP, Federal Energy Regulatory Commission (FERC)