Energy Transfer LP is an energy-infrastructure partnership with natural-gas, crude-oil, natural-gas-liquids, and refined-products assets. Its subsidiary Transwestern Pipeline Company, LLC is sponsoring the proposed Desert Southwest Pipeline expansion from West Texas through New Mexico into Arizona.

Energy Transfer announced a positive final investment decision on August 6, 2025. That announcement described 516 miles of 42-inch pipeline, 1.5 billion cubic feet per day of design capacity, nine compressor stations, an estimated cost of about $5.3 billion, and expected service in the fourth quarter of 2029. Current applicant materials describe an approximately 520-mile project capable of delivering up to 2.3 billion cubic feet per day. Those later figures should be used as the current applicant description, while recognizing that engineering and environmental review remain underway.

Transwestern is using FERC’s pre-filing process under PF26-9-000. Pre-filing is not a construction certificate or project approval. APS, the City of Mesa, Salt River Project, Tucson Electric Power, and UniSource Energy Services separately announced commitment plans for the expansion. The public sources do not establish that any particular Desert Southwest capacity is dedicated to the Saguaro Power Plant expansion.

Timeline & Milestones

Scroll or swipe to explore

  1. Completed Energy transfer project record

    Energy Transfer announced the Desert Southwest expansion

    The initial announcement described 516 miles, 1.5 Bcf/d, a $5.3 billion estimated cost, and projected fourth-quarter 2029 service.

  2. Completed Energy transfer project record

    Transwestern opened a binding open season

    The Energy Transfer subsidiary sought binding shipper commitments through October 25, 2025.

  3. Completed Energy transfer project record

    FERC pre-filing docket PF26-9-000 opened

    Transwestern entered FERC’s pre-filing process; opening a pre-filing docket was not project approval.

  4. Current Energy transfer project record

    FERC accepted the project into pre-filing review

    Environmental review and public scoping proceeded under PF26-9-000.

  5. Proposed Energy transfer project record

    Applicant projects fourth-quarter 2029 service

    The schedule remains contingent on engineering, environmental review, permits, and FERC authorization.

How to get involved

Participation guides not yet published. Step-by-step ways to take part will appear here when this profile is completed.

Upcoming

No upcoming events currently posted.

Past events

FERC scoping comments due — Desert Southwest Pipeline

Deadline for public input on FERC pre-filing environmental scoping. Docket PF26-9-000. Energy Transfer / Transwestern expansion, ~520 miles, 48-inch, up to 2.3 Bcf/d Permian-to-Arizona/New Mexico.

Full date and time
Wednesday, August 5, 2026
Status
Completed