Synopsis
Rosebud Energy Center is a proposed utility-scale solar-and-battery project on farmland south of Maricopa, beside Nissan’s test track and along North White and Parker roads in unincorporated Pinal County. The request would redesignate approximately 534.60 acres from Employment to Green Energy Production.
The Citizens Advisory Committee and Planning and Zoning Commission recommended approval, but those are recommendations. The November 18 Board hearing is in the official agenda; a final Board action was not found in the retrieved record. The plan amendment alone would not authorize construction or establish a utility interconnection.
The community tracker currently labels this project Planning. The dated record and official links below should be used to check that label and any later change.
Links
Find current Arizona laws by statute number, keyword, subject, or an exact quoted phrase.
Official Board agenda
Official Board staff report
Official commission record
Official advisory committee record
Official monitoring portal
Local reporting
Related project profiles
- Arizona Independent Technology Campus Local reporting discusses both proposals in the Maricopa-area energy and technology development context; they are separate applications.
Timeline & Milestones
Scroll or swipe to explore
How to get involved
How to participate in Rosebud Energy Center — PZ-PA-012-26; Resolution No. 2026-PZ-PA-012-26
Use the verified project record and monitor the correct agency for the next live notice.
Use PZ-PA-012-26 in correspondence. The scheduled November 18, 2026 Board hearing has passed, and no currently open comment period was verified. Confirm the Board’s action before describing the request as approved or denied.
-
Save the exact identifiers: PZ-PA-012-26; Resolution No. 2026-PZ-PA-012-26
Use PZ-PA-012-26; Resolution No. 2026-PZ-PA-012-26 in searches, subject lines, comments, and records requests. Do not substitute a similarly named project or general-policy docket. -
Read the project-specific record
Open the official record linked below and verify the present status, scope, meeting location, submission method, and deadline before acting. -
Treat old deadlines as closed
The September 11 committee, October 15 commission, and November 18 Board dates are past. No later public-comment deadline was verified. -
Monitor the next live notice
Monitor Pinal County hearing notices and agendas for PZ-PA-012-26. Ask the Planning Division for the Board’s official action and any subsequent zoning, air, or energy-siting cases.
Upcoming
No upcoming events currently posted.
Past events
Pinal County Board hearing — Rosebud Energy Center
Scheduled public hearing for PZ-PA-012-26, a request to redesignate approximately 534.60 acres for solar generation and battery storage. The October Planning and Zoning recommendation was 8–0. The final Board action was not verified in the retrieved official record; do not infer that the requested motion passed.
- Full date and time
- Wednesday, November 18, 2026 · 9:30 am (America/Phoenix)
- Status
- Completed
Related projects: Rosebud Energy Center
Related entities: Pinal County, Nissan North America Inc., Rosebud Energy Center, Rose Law Group