Synopsis
“La Osa Power Plant 2” is a tracker label, not an official separately named project; county records described generation within the umbrella La Osa Project / La Osa Energy Center.
No separate Plant 2 application, docket, or permit was found. The original concept mentioned two plants, the later reduced concept was described as one, and the umbrella rezoning/PAD was denied.
The community tracker currently labels this project Dead. The dated record and official links below should be used to check that label and any later change.
Links
Find current Arizona laws by statute number, keyword, subject, or an exact quoted phrase.
Official county case records
Applicant materials in official record
Official county decisions
Official meeting records
Official monitoring portals
Credible secondary context
Timeline & Milestones
Scroll or swipe to explore
How to get involved
How to participate in La Osa Power Plant 2 — PZ-PA-011-25; PZ-003-26; PZ-PD-003-26
Use the verified project record and monitor the correct agency for the next live notice.
The verified county identifiers are PZ-PA-011-25, PZ-003-26, and PZ-PD-003-26. The 2026 rezoning/PAD was denied; no open deadline was found. Any renewed application must be noticed again.
-
Save the exact identifiers: PZ-PA-011-25; PZ-003-26; PZ-PD-003-26
Use PZ-PA-011-25; PZ-003-26; PZ-PD-003-26 in searches, subject lines, comments, and records requests. Do not substitute a similarly named project or general-policy docket. -
Read the project-specific record
Open the official record linked below and verify the present status, scope, meeting location, submission method, and deadline before acting. -
Treat old deadlines as closed
The August 26, 2026 hearing is closed. There is no separately verified Plant 2 comment process. -
Monitor the next live notice
Monitor Pinal County hearing notices and agendas, or contact planningdivision@pinal.gov / 520-509-3555, explicitly stating PZ-PA-011-25, PZ-003-26, and PZ-PD-003-26.
Additional Resources
Upcoming
No upcoming events currently posted.
Past events
Pinal County Board of Supervisors — La Osa rezoning denied
Supervisors voted 4–1 against the La Osa rezoning. Campus had been reduced from 50+ buildings to 11 data halls plus associated gas generation. Overflow rooms were used.
- Full date and time
- Wednesday, August 26, 2026
- Status
- Completed
Related projects: La Osa Data Center, La Osa Power Plant 1, La Osa Power Plant 2
Related entities: Vermaland LLC, Pinal County