Pinal Airpark MZJ

Entities

Owner: Pinal County State of Arizona (AZ)

Regulatory or jurisdictional authority: Pinal County

Location: Pinal County

Clean Air Act context: U.S. Environmental Protection Agency (EPA)

Statuses Planning, Expanding

Synopsis

Pinal Airpark’s 2026 Airport Master Plan Update is a 20-year planning process for county-owned airport MZJ.

The master plan is not itself construction authorization or a NEPA decision.

The community tracker currently labels this project Planning, and Expanding. The dated record and official links below should be used to check that label and any later change.

Timeline & Milestones

Scroll or swipe to explore

  1. Completed Initial profile public process

    Pinal Airpark Master Plan open house

    Drop-in open house for the 2026 Airport Master Plan (20-year vision). No formal presentation.

    Pinal Airpark Master Plan open house

    Drop-in open house for the 2026 Airport Master Plan (20-year vision). No formal presentation.

    Full date and time
    Thursday, August 6, 2026 · 4:00 pm – Thursday, August 6, 2026 · 7:00 pm (America/Phoenix)
    Duration
    3 hr
    Status
    Completed

    Related projects: Pinal Airpark MZJ

    Related entities: State of Arizona (AZ), Pinal County

  2. Completed Researched project record

    Prior master plan finalized in September 2015

    Exact day not stated.

  3. Completed Researched project record

    FAA approved prior Airport Layout Plan

    Approval date stated in the 2026 draft.

  4. Completed Researched project record

    Open-house notice posted

    County announced the first workshop.

  5. Completed Researched project record

    Public Information Meeting 1

    First of three planned workshops was held.

  6. Planned Researched project record

    Public Information Meetings 2 and 3

    Planned for alternatives and preferred program/phasing; dates unknown.

How to get involved

How to participate in Pinal Airpark MZJ — MZJ; prior plan ADOT project E3S3R

Use the verified project record and monitor the correct agency for the next live notice.

Use “MZJ 2026 Airport Master Plan Update” in correspondence; later public workshops are planned.

  1. Save the exact identifiers: MZJ; prior plan ADOT project E3S3R

    Use MZJ; prior plan ADOT project E3S3R in searches, subject lines, comments, and records requests. Do not substitute a similarly named project or general-policy docket.
  2. Read the project-specific record

    Open the official record linked below and verify the present status, scope, meeting location, submission method, and deadline before acting.
  3. Treat old deadlines as closed

    The August 6, 2026 first workshop is closed. No dates were verified for workshops 2 and 3.
  4. Monitor the next live notice

    Monitor the county Pinal Airpark page; email ray.telles@pinal.gov or call 520-866-6529 for future workshop and comment details.

Upcoming

No upcoming events currently posted.

Past events

Pinal Airpark Master Plan open house

Drop-in open house for the 2026 Airport Master Plan (20-year vision). No formal presentation.

Full date and time
Thursday, August 6, 2026 · 4:00 pm – Thursday, August 6, 2026 · 7:00 pm (America/Phoenix)
Duration
3 hr
Status
Completed

Related projects: Pinal Airpark MZJ

Related entities: State of Arizona (AZ), Pinal County