Synopsis
Project Midway is a proposed data-center campus on approximately 215 acres at Selma Highway and Midway Road.
The plan amendment is approved, but the rezoning and PAD were continued without a return date. No project-specific ACC, ADEQ, or NEPA docket was verified.
The community tracker currently labels this project Delayed, and Zoning. The dated record and official links below should be used to check that label and any later change.
Links
Find current Arizona laws by statute number, keyword, subject, or an exact quoted phrase.
Official county case records
Official county decisions
Official monitoring portals
Credible secondary context
Timeline & Milestones
Scroll or swipe to explore
How to get involved
How to participate in Project Midway Data Center — PZ-PA-013-25; PZ-008-26; PZ-PD-007-26
Use the verified project record and monitor the correct agency for the next live notice.
Use all three county identifiers; the pending cases are PZ-008-26 and PZ-PD-007-26.
-
Save the exact identifiers: PZ-PA-013-25; PZ-008-26; PZ-PD-007-26
Use PZ-PA-013-25; PZ-008-26; PZ-PD-007-26 in searches, subject lines, comments, and records requests. Do not substitute a similarly named project or general-policy docket. -
Read the project-specific record
Open the official record linked below and verify the present status, scope, meeting location, submission method, and deadline before acting. -
Treat old deadlines as closed
The July 16, 2026 hearing was continued with no date. That meeting is closed; confirm a newly posted notice before attending. -
Monitor the next live notice
Monitor official Pinal notices/agendas. Email planningdivision@pinal.gov or call 520-509-3555, label both pending case numbers, and ask that comments be included in the record.
Additional Resources
Upcoming
No upcoming events currently posted.
Past events
Pinal County Planning & Zoning — Project Midway continued
Commission unanimously postponed rezoning and overlay for the ±215.8-acre data center near Casa Grande. ED3 asked for delay over self-generation questions. No new hearing date set; county must re-notice before it returns.
- Full date and time
- Thursday, July 16, 2026
- Status
- Completed
Related projects: Project Midway Data Center
Related entities: LPI Group, Pinal County