Connections
Entity connections
- Regulatory or jurisdictional authority: Arizona Corporation Commission (ACC)
- Regulatory or jurisdictional authority: Arizona Power Plant and Transmission Line Siting Committee
- Owned by: Kindle Energy
- Regulatory or jurisdictional authority: Pinal County
- Regulatory or jurisdictional authority: Pinal County Air Quality Control District
Connected projects
- Owner: Sunridge Power Plant
Synopsis
Synopsis not yet published. This part of the profile has not been completed.
Links
Connected entity profiles
Connected project profiles
Sources from connected projects
- Sunridge Power Plant Sunridge Power project website
- Sunridge Power Plant Official state case file — ACC Case 266
- Sunridge Power Plant Official notice for the September 2026 hearing
- Sunridge Power Plant Developer’s presentation to Pinal County supervisors
- Sunridge Power Plant News report on the county Planning Commission meeting
- Sunridge Power Plant News report on the county’s approval
Timeline & Milestones
Project process not yet mapped. Required and voluntary milestones will appear here when this profile is completed.
How to get involved
Participation guides not yet published. Step-by-step ways to take part will appear here when this profile is completed.
Upcoming
No upcoming events currently posted.
Past events
Sunridge Power CEC Hearing — Continued Sessions
Continued evidentiary sessions Wednesday–Friday as necessary. Daily hours 9:00 a.m.–5:00 p.m. unless a site tour is scheduled.
- Full date and time
- Wednesday, September 9, 2026 · 9:00 am – Friday, September 11, 2026 · 5:00 pm (America/Phoenix)
- Duration
- 2 days 8 hr
- Meeting ID
- 818 3041 5284
- Passcode
- None
- Dial in
- +1 (646) 558-8656
- Status
- Scheduled
ACC Line Siting Case No. 266. Docket L-21419A-26-0314-00266. CEC for 1,360 MW combined-cycle plant and ~5-mile 500 kV gen-tie in unincorporated Pinal County. Chairman Adam Stafford. Public comment may also be taken at the start of each hearing day at the Chairman's discretion. A Committee tour may shift a day's start.
Sunridge Power CEC Hearing — Public Comment
Special evening public-comment session. Comment in person, on Zoom, or by phone.
- Full date and time
- Tuesday, September 8, 2026 · 5:30 pm (America/Phoenix)
- Meeting ID
- 818 3041 5284
- Passcode
- None
- Dial in
- +1 (646) 558-8656
- Status
- Scheduled
ACC Line Siting Case No. 266. Docket L-21419A-26-0314-00266. CEC for 1,360 MW combined-cycle plant and ~5-mile 500 kV gen-tie in unincorporated Pinal County. Chairman Adam Stafford. Public comment may also be taken at the start of each hearing day at the Chairman's discretion. A Committee tour may shift a day's start.
Sunridge Power CEC Hearing — Day 1
Evidentiary hearing before the Arizona Power Plant and Transmission Line Siting Committee on Sunridge Power LLC's Certificate of Environmental Compatibility.
- Full date and time
- Tuesday, September 8, 2026 · 10:00 am – Tuesday, September 8, 2026 · 5:00 pm (America/Phoenix)
- Duration
- 7 hr
- Meeting ID
- 818 3041 5284
- Passcode
- None
- Dial in
- +1 (646) 558-8656
- Status
- Scheduled
ACC Line Siting Case No. 266. Docket L-21419A-26-0314-00266. CEC for 1,360 MW combined-cycle plant and ~5-mile 500 kV gen-tie in unincorporated Pinal County. Chairman Adam Stafford. Public comment may also be taken at the start of each hearing day at the Chairman's discretion. A Committee tour may shift a day's start.