Connections
Entity connections
- Agency or jurisdiction: Arizona Power Plant and Transmission Line Siting Committee
- Parent organization or jurisdiction: State of Arizona (AZ)
- Regulates or oversees: Sunridge Power, LLC
Connected projects
- Regulatory or jurisdictional authority: Eloy Valley Energy Center III
- Regulatory or jurisdictional authority: Luckett Road Data Center
- Regulatory or jurisdictional authority: Saguaro Power Plant
- Regulatory or jurisdictional authority: Steele Energy Center
- Regulatory or jurisdictional authority: Sunridge Power Plant
Synopsis
Arizona Corporation Commission (ACC) is a public regulatory body. It is connected to 5 known projects affecting Red Rock and Missile Base.
Parent government or authority: State of Arizona (AZ).
Regulatory or jurisdictional authority: Eloy Valley Energy Center III, Luckett Road Data Center, Saguaro Power Plant, Steele Energy Center, and Sunridge Power Plant.
Links
Find current Arizona laws by statute number, keyword, subject, or an exact quoted phrase.
Official information
Connected entity profiles
Connected project profiles
Sources from connected projects
- Eloy Valley Energy Center III ACC Docket L-21375A-25-0252-00256
- Eloy Valley Energy Center III Eloy Valley CEC filing
- Eloy Valley Energy Center III Eloy Valley CEC materials
- Eloy Valley Energy Center III Pinal P&Z action summary
- Eloy Valley Energy Center III Recorded Resolution 2026-PZ-009-26
- Eloy Valley Energy Center III ACC public-comment portal
- Eloy Valley Energy Center III Official hearing notices
- Eloy Valley Energy Center III NextEra Energy Resources — Eloy Valley Solar
- Eloy Valley Energy Center III Pinal Post — Eloy Valley Energy Center III approval
- Luckett Road Data Center Luckett Road North and South Data Centers
- Luckett Road Data Center Luckett Road North Specific Plan
- Luckett Road Data Center Luckett Road South Specific Plan
- Luckett Road Data Center Luckett Road North hearing notice
- Luckett Road Data Center Luckett Road South hearing notice
- Luckett Road Data Center Ordinance 2026.002 — North
- Luckett Road Data Center Ordinance 2026.003 — South
- Luckett Road Data Center January 6 Council hearing video
- Luckett Road Data Center Marana Development Projects dashboard
- Luckett Road Data Center Marana public notices
- Luckett Road Data Center Town referendum review
- Luckett Road Data Center Beale Infrastructure — Marana data center
- Luckett Road Data Center Tucson Spotlight — Marana data-center noise rules
- Saguaro Power Plant Official state case — Saguaro Case 272
- Saguaro Power Plant APS Saguaro Power Plant Expansion Project
- Saguaro Power Plant Official notice — December 7–11 Saguaro hearing
- Saguaro Power Plant Saguaro virtual open house
- Saguaro Power Plant Existing Saguaro Title V permit
- Saguaro Power Plant APS Saguaro expansion — current documents and access links
- Saguaro Power Plant PZ-022-26 — November 19 county rezoning item
- Saguaro Power Plant Permit V20692.R01 document
- Saguaro Power Plant Saguaro permit technical support document
- Saguaro Power Plant Saguaro CEC application — applicant filing
- Saguaro Power Plant Saguaro expansion air-permit application
- Saguaro Power Plant Pinal industrial permit public notices
- Saguaro Power Plant Saguaro expansion water-resource assessment
- Saguaro Power Plant Saguaro expansion traffic study
- Saguaro Power Plant Saguaro corrected 90-day filing — October 30, 2026
- Saguaro Power Plant Saguaro October 16 pre-filing conference transcript
- Saguaro Power Plant Arizona law — ACC review after a committee decision
- Saguaro Power Plant ACC eFiling — written public comments
- Saguaro Power Plant Line Siting Committee — official hearings and changes
- Saguaro Power Plant Related project — APS Sonoran Gateway
- Saguaro Power Plant Sonoran Gateway November 2026 newsletter
- Saguaro Power Plant Watch the Saguaro hearing — not a speaking connection
- Saguaro Power Plant Speak at December 7 Saguaro public comment — Zoom
- Saguaro Power Plant Energy Transfer announces Desert Southwest project
- Saguaro Power Plant Arizona utilities announce commitment plans
- Steele Energy Center Steele Energy Center eDocket
- Steele Energy Center Steele Energy Center Case 271 hearing notice
- Steele Energy Center Steele Energy Center project website
- Steele Energy Center ACC public-comment portal
- Sunridge Power Plant Sunridge Power project website
- Sunridge Power Plant Official state case file — ACC Case 266
- Sunridge Power Plant Official notice for the September 2026 hearing
- Sunridge Power Plant Developer’s presentation to Pinal County supervisors
- Sunridge Power Plant News report on the county Planning Commission meeting
- Sunridge Power Plant News report on the county’s approval
Timeline & Milestones
Project process not yet mapped. Required and voluntary milestones will appear here when this profile is completed.
How to get involved
Participation guides not yet published. Step-by-step ways to take part will appear here when this profile is completed.
Upcoming
Steele Energy Center CEC hearing — Case 271
America/Phoenix
Radisson Hotel Casa Grande 777 N Pinal Ave, Casa Grande, AZ, 85122
Arizona Power Plant and Transmission Line Siting Committee hearing on the application for a Certificate of Environmental Compatibility for an approximately 1,400-MW natural-gas plant. The hearing may continue through December 4, starting at 9:00 a.m. on later days.
- Full date and time
- Monday, November 30, 2026 · 10:00 am (America/Phoenix)
- Status
- Scheduled
The notice says schedule changes and remote-access details will be posted on the applicant and ACC sites; verify those details before attending remotely.
Related projects: Steele Energy Center
Related entities: Steele Energy Center, LLC, Arizona Corporation Commission (ACC), Arizona Power Plant and Transmission Line Siting Committee, Pinal County
Steele Energy Center — dedicated public-comment session
America/Phoenix
Radisson Hotel Casa Grande 777 N Pinal Ave, Casa Grande, AZ, 85122
Special public-comment session for ACC Line Siting Case 271. The official notice allows comments in person, by telephone, or by video conference; the ACC will post remote-access details at least 24 hours before the session.
- Full date and time
- Monday, November 30, 2026 · 5:30 pm (America/Phoenix)
- Status
- Scheduled
No telephone number or video link was published in the notice retrieved for this profile.
Related projects: Steele Energy Center
Related entities: Steele Energy Center, LLC, Arizona Corporation Commission (ACC), Arizona Power Plant and Transmission Line Siting Committee, Pinal County
Past events
Sunridge Power CEC Hearing — Continued Sessions
Continued evidentiary sessions Wednesday–Friday as necessary. Daily hours 9:00 a.m.–5:00 p.m. unless a site tour is scheduled.
- Full date and time
- Wednesday, September 9, 2026 · 9:00 am – Friday, September 11, 2026 · 5:00 pm (America/Phoenix)
- Duration
- 2 days 8 hr
- Meeting ID
- 818 3041 5284
- Passcode
- None
- Dial in
- +1 (646) 558-8656
- Status
- Scheduled
ACC Line Siting Case No. 266. Docket L-21419A-26-0314-00266. CEC for 1,360 MW combined-cycle plant and ~5-mile 500 kV gen-tie in unincorporated Pinal County. Chairman Adam Stafford. Public comment may also be taken at the start of each hearing day at the Chairman's discretion. A Committee tour may shift a day's start.
Sunridge Power CEC Hearing — Public Comment
Special evening public-comment session. Comment in person, on Zoom, or by phone.
- Full date and time
- Tuesday, September 8, 2026 · 5:30 pm (America/Phoenix)
- Meeting ID
- 818 3041 5284
- Passcode
- None
- Dial in
- +1 (646) 558-8656
- Status
- Scheduled
ACC Line Siting Case No. 266. Docket L-21419A-26-0314-00266. CEC for 1,360 MW combined-cycle plant and ~5-mile 500 kV gen-tie in unincorporated Pinal County. Chairman Adam Stafford. Public comment may also be taken at the start of each hearing day at the Chairman's discretion. A Committee tour may shift a day's start.
Sunridge Power CEC Hearing — Day 1
Evidentiary hearing before the Arizona Power Plant and Transmission Line Siting Committee on Sunridge Power LLC's Certificate of Environmental Compatibility.
- Full date and time
- Tuesday, September 8, 2026 · 10:00 am – Tuesday, September 8, 2026 · 5:00 pm (America/Phoenix)
- Duration
- 7 hr
- Meeting ID
- 818 3041 5284
- Passcode
- None
- Dial in
- +1 (646) 558-8656
- Status
- Scheduled
ACC Line Siting Case No. 266. Docket L-21419A-26-0314-00266. CEC for 1,360 MW combined-cycle plant and ~5-mile 500 kV gen-tie in unincorporated Pinal County. Chairman Adam Stafford. Public comment may also be taken at the start of each hearing day at the Chairman's discretion. A Committee tour may shift a day's start.
Eloy Valley Energy Center III CEC Hearing
Line Siting Case 256. Docket L-21375A-25-0252-00256. CEC for ~1.7-mile 230 kV gen-tie from solar + BESS to WAPA ED-5. Public comment evening was Jan 20 at 5:30 p.m.
- Full date and time
- Tuesday, January 20, 2026 · 1:00 pm – Friday, January 23, 2026 · 5:00 pm (America/Phoenix)
- Duration
- 3 days 4 hr
- Status
- Completed
Related projects: Eloy Valley Energy Center III
Related entities: NextEra Energy Resources, LLC, Arizona Corporation Commission (ACC), Arizona Power Plant and Transmission Line Siting Committee, Pinal County