Synopsis
APS proposes two new units totaling about 720 MW at the existing Saguaro Power Plant, with an estimated 2030 completion.
No verified project-specific ACC line-siting docket, expansion air-permit number, or official queue ID was found.
The community tracker currently labels this project Planning. The dated record and official links below should be used to check that label and any later change.
Links
Find current Arizona laws by statute number, keyword, subject, or an exact quoted phrase.
Applicant project resources
Official air permits
Official technical records
Official monitoring portals
Timeline & Milestones
Scroll or swipe to explore
How to get involved
How to participate in Saguaro Power Plant — Existing air permit V20692.R01
Use the verified project record and monitor the correct agency for the next live notice.
Use “Saguaro Power Plant Expansion Project” for applicant feedback and V20692.R01 only when discussing the existing air permit or a related new notice.
-
Save the exact identifiers: Existing air permit V20692.R01
Use Existing air permit V20692.R01 in searches, subject lines, comments, and records requests. Do not substitute a similarly named project or general-policy docket. -
Read the project-specific record
Open the official record linked below and verify the present status, scope, meeting location, submission method, and deadline before acting. -
Treat old deadlines as closed
APS’s preferred August 31, 2026 early-feedback date has passed, but APS says feedback remains welcome. -
Monitor the next live notice
Email saguaroexpansion@aps.com or call 520-231-4411. Monitor Pinal industrial permit notices and use any new permit number exactly as noticed.
Upcoming
No upcoming events currently posted.
Past events
APS Saguaro expansion — comment deadline
APS asked the public to submit comments by this date for timely consideration in early permitting. No Line Siting hearing date has been set.
- Full date and time
- Monday, August 31, 2026
- Status
- Completed
Related projects: Saguaro Power Plant
Related entities: Arizona Public Service (APS)
APS Saguaro expansion open house
Second in-person open house for the Saguaro expansion.
- Full date and time
- Wednesday, June 17, 2026
- Status
- Completed
Related projects: Saguaro Power Plant
Related entities: Pinnacle West Capital Corporation, Arizona Public Service (APS)
APS Saguaro expansion open house (Red Rock)
In-person community open house for the proposed ~720 MW expansion (two new units). Contact saguaroexpansion@aps.com / (520) 231-4411.
- Full date and time
- Monday, June 15, 2026
- Status
- Completed
Related projects: Saguaro Power Plant
Related entities: Pinnacle West Capital Corporation, Arizona Public Service (APS)